Bullet Train Milestone: Second 100m Steel Bridge Span Launched Over NH-48 in Gujarat
1. Second 100-Meter Span Successfully LaunchedThe National High Speed rail Corporation Limited (NHSRCL) confirmed that the second 100-meter span of the steel bridge was launched across NH-48 on september 3. This completes the 200-meter-long steel bridge comprising two spans, each measuring 100 meters.The first span was launched in April 2025, and the second has now been seamlessly placed, bringing this segment to completion.
2. Massive Structure With Staggering WeightThis steel bridge is no ordinary construction — it’s a giant engineering marvel:
- Length: 200 meters (2 x 100m spans)
- Height: 14.6 meters
- Width: 14.3 meters
- Weight: 2,884 metric tons
3. Engineering Precision on NH-48NH-48 is among India’s busiest highways, connecting Delhi, Mumbai, and Chennai, and it handles six lanes of traffic (three on each side). Launching such a massive span without halting traffic was a huge challenge.To achieve this:
- The 100m span was slid across three lanes.
- A carefully timed schedule ensured minimal disruption.
- Traffic movement remained smooth and safe throughout the process.
4. Complex assembly ProcessThe bridge wasn’t built on the highway directly but carefully assembled on temporary trestles at a height of 14.9 meters above the ground.The launch mechanism included:
- Two semi-automatic jacks, each capable of lifting 250 tons.
- Mac-alloy bars for precise movement.
- An automatic sliding system for steady placement.
5. Use of High-Strength MaterialsTo withstand the stresses of high-speed trains, the bridge uses top-quality materials and methods:
- 1,14,172 Tor-Shear Type High Strength (TTHS) bolts hold the bridge together.
- A C5 system painting ensures superior corrosion protection.
- Elastomeric bearings improve flexibility and load absorption.
6. Part of a Bigger Picture: 28 Steel BridgesThis isn’t a standalone achievement. The Mumbai-Ahmedabad corridor will feature a total of 28 steel bridges:
- 17 in Gujarat
- 11 in Maharashtra
7. Why Steel Bridges Matter for the Bullet TrainUnlike conventional bridges, steel bridges are crucial for high-speed rail due to:
- Strength: Withstanding the immense dynamic loads of bullet trains.
- Longevity: 100-year design lifespan.
- Precision: Required data-alignment for trains running at speeds of 320 km/h.
8. Seamless Coordination With Highway UsersLaunching a massive bridge across NH-48 required not just engineering skill but also logistical precision. NHSRCL coordinated with highway authorities to:
- Minimize traffic disruption.
- Schedule the launch during safe windows.
- Maintain smooth traffic flow on all six lanes.
9. Bullet train Project: A National DreamThe Mumbai-Ahmedabad Bullet train project is India’s first high-speed rail corridor. Once complete, it will:
- Cover 508 km in just 2-3 hours.
- Operate at speeds up to 320 km/h.
- Transform travel between India’s financial capital and industrial hub.
10. Symbol of India’s Engineering ProwessThe launch of the second span demonstrates not just technical expertise but also India’s ability to deliver on world-class infrastructure projects. From advanced mechanization to material innovation, the bridge reflects the country’s march toward modern, future-ready transportation.
Final WordThe successful launch of the second 100-meter steel bridge span over NH-48 is more than an engineering milestone — it’s a symbol of India’s progress toward its first bullet train. With 28 such steel bridges planned, each achievement is a step closer to realizing a world-class high-speed rail network that will redefine travel in India.Disclaimer:The views and opinions expressed in this article are those of the author and do not necessarily reflect the official policy or position of any agency, organization, employer, or company. All information provided is for general informational purposes only. While every effort has been made to ensure accuracy, we make no representations or warranties of any kind, express or implied, about the completeness, reliability, or suitability of the information contained herein. Readers are advised to verify facts and seek professional advice where necessary. Any reliance placed on such information is strictly at the reader’s own risk.